Design Brief: July Updates

At the last design meeting, Design Lead Bob reviewed the entire project site, showing the water intake location and tracing the transmission line to the proposed distribution tanks and then on to the distribution network.  Above is a schematic digital terrain model of our project site.  The team is working to refine it for development of plan and profile sheets.

The next meeting will be the 30% Design Plan Meeting on Tuesday, Aug 14th.